US 101 HOV Lanes - Wilfred

Description: In Rohnert Park, from south of Wilfred Avenue to Santa Rosa Avenue - Widen from 4 to 6 lanes for high occupancy vehicle lanes

  • Project Information
  • Contacts
  • Cost by Fund Source
  • Cost by Component
  • Schedule
  • Map
  • Closeout Info
Project Location
County
Sonoma
City Rohnert Park
Zip Code 94928, 95407
 
Senate District
03
Assembly District 06
Congressional District 06
 
Caltrans District
04
 
 
County/State Route Sonoma 101
Postmile Begin/End 13.9 15.5
Project Benefits
 Benefit Baseline Actual
Daily Travel Time Savings (hours)  2841    3216  
Lane Miles Added (HOV)  3.0      
Peak Period Time Savings (minutes)  207420    234800  
 
Project Contacts Agency Contact Person Telephone E-mail
Environmental Phase
Caltrans Doanh Nguyen (510) 286-6128   doanh_nguyen@dot.ca.gov
Design (PS&E) Phase
Caltrans Doanh Nguyen (510) 286-6128   doanh_nguyen@dot.ca.gov
Right of Way Phase
Caltrans Doanh Nguyen (510) 286-6128   doanh_nguyen@dot.ca.gov
Construction Phase
Caltrans Doanh Nguyen (510) 286-6128   doanh_nguyen@dot.ca.gov
 
Corridor System Management Plan
Caltrans Juliana Gum (510) 286-4579   juliana_gum@dot.ca.gov
Project Cost Baseline Summary (Dollars Shown are in Thousands) 2
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Bond Funding
RIP Augmentation
$0 $13,315 $13,315
CMIA
$44,800 $-15,520 $29,280
Non-bond Funding
State/Federal*
$18,433 $-1,661 $16,772
Local**
$20,000 $0 $20,000
Non Budgeted ETC
$0 $0 $0
 
Total**** $83,233 $-3,866 $79,367

**** Totals may not add up exactly to column amounts due to rounding

# Approved is planned budget

Project Cost Baseline Summary (Dollars Shown are in Thousands)
  Adopted Program
(06/07/07)
a
Approved Changes
(12/31/2023
b=c-a
Current Approved
(12/31/2023
c
Cost to Date**
(12/31/2023
d
 
Environmental
$743 $4,275 $5,018 $0
Design(PS&E)
$4,550 $3,554 $8,104 $0
Right of Way
$8,840 $-260 $8,580 $2,128
Construction
$69,100 $-11,435 $57,665 $47,896
 
Total* $83,233 $-3,866 $79,367 $50,024

* Totals may not add up exactly to column amounts due to rounding

** Totals include all actual project funds expenditures. Cost to date expenditure variances are explained in quarterly reports and/or Close-out reports.

Project Schedule Baseline Summary
(Schedule Changes and Variances in Months) Adopted Program
(06/07/07)
a
Approved Changes
(mm/dd/yyyy)
b
Current Approved
(12/31/2023)
c
% Complete
(12/31/2023)
d
Schedule Forecast
(12/31/2023)
e
Schedule Variance
(months)
f=c-e
Begin Environmental Phase

End Environmental Phase
01/01/2003 

12/01/2006 
 

 
01/01/2003 

12/01/2006 
100  01/01/2003 

11/30/2006 


Begin Design (PS&E) Phase

End Design (PS&E) Phase
07/01/2005 

08/01/2008 
 

 
07/01/2005 

08/01/2008 
100  10/01/2004 

08/15/2008 


Begin Right of Way Phase

End Right of Way Phase
12/01/2006 

08/01/2008 
 

 
12/01/2006 

08/01/2008 
100  11/30/2006 

08/30/2008 


-1 
Begin Construction Phase

End Construction Phase
01/01/2009 

12/01/2011 
 

 
03/01/2009 

12/01/2013 
100  05/14/2009 

06/28/2013 
-2 

Begin Closeout Phase

End Closeout Phase
01/02/2012 

01/02/2013 
 

 
01/01/2014 

01/01/2015 
07/01/2013 

12/31/2015 


-12 
Corridor System Management Plan
Adoption Date 09/01/2010    09/01/2010   
Implementation Date 09/01/2010    09/01/2009   
????????
Project Benefits
Benefit Baseline Actual
Daily Travel Time Savings (hours) 2841 3216
Lane Miles Added (HOV) 3.0
Peak Period Time Savings (minutes) 207420 234800

Bond Funding Cost
Adopted:
$44,800,000
Current Approved:
$1,600,000
Actual Expenditures:
$1,599,751

 

Status as of December 31, 2023.